Major Projects <Domestic> Civil and Road Project

Project Name : Pavement Work in Four Tunnels including HADANASHI Tunnel
on Shin-Tomei Expressway
Client : Central Nippon Expressway Company Limited (C-NEXCO)
LocationOINO Town-OIDAIRA Town
Construction Period26.Feburuary.2013 - 18.Octorber.2014

[Mainly Quantity]

Cutting & Embankment53,894 m³Asphalt Pavement9,444 m²
Subbase & Base Course66,211 m²Concrete Pavement68,921 m²
Other WorkTunnel , Slope Protection , Drainage , Electric Pipe , Removal
Ancillary and Miscellaneous Works
FacilitiesTemporary Aggregate Plant
Special FeatureTunnel Mouse Construction
Slip Form Method for Concrete Pavement (Non-Formwork)
Continuously Reinforced Concrete Pavement