Major Projects <Domestic> Road Project
Project Name : | NARITA Pavement Work on the National Capital Region Central Loop Road (KEN-O-DO) |
---|---|
Client : | East Nippon Expressway Company Limited (E-NEXCO) |
Location | INASHIKI City - NARITA City | |||
---|---|---|---|---|
Construction Period | 7.March.2014-29.July.2015 | |||
Road Length | 8.89 miles (14,300 m) |
[Mainly Quantity]
Subbase and Base Course | 194,163 m² | Guard Rail | 28,408 m | |
---|---|---|---|---|
Asphaltic Bound Base | 189,719 m² | Fence | 21,833 m | |
Asphalt Mixture | 84,304 tons | Drainage | 14,089 m | |
Waterproofing for Bridge Slab | 13,663 m² | Electric Pipe | 12,022 m | |
Other Work | Median, Planting, Ancillary and Miscellaneous Works |
Facilities | Temporary Asphalt & Aggregate Plant | |||
---|---|---|---|---|
Special Feature | High-performance Waterproofing for Bridge Slab (Life-time : 30years), Hybrid Pavement, Drainage Pavement |